Size & quantities
A larger room needs more materials and labour. Cabinet length and tile area matter more than the room name.

A USEFUL STARTING POINT
Honest planning ranges before you invite us over. The measured quote shows the detail, so you know what you are agreeing to.
THE PRICE GUIDE
These ranges help you plan. Your quote depends on the measured scope, site conditions, material selection and any applicable taxes, stated clearly before acceptance.

| Renovation work | Typical range | Time / pricing basis |
|---|---|---|
| Kitchen renovation | RM 18,000–65,000 | 3–8 weeks |
| Bathroom renovation | RM 8,000–22,000 | 2–3 weeks |
| Whole house renovation | RM 65,000–180,000 | 10–16 weeks |
| Kitchen & rear extensions | RM 35,000–95,000 | 8–12 weeks |
| Roof leak repair & reroofing | RM 800–8,000 | 1–5 days |
| Shop & office renovation | RM 25,000–100,000 | 4–8 weeks |
| Wet works & tiling | RM 12–28 / sq ft | Prepared area, tile choice and laying pattern |
| Plaster ceiling & lighting | RM 6–12 / sq ft | Ceiling area; lighting fittings priced separately |
| Built-in carpentry | RM 350–650 / ft | Board, hardware, depth and internal layout |
| Reroofing | RM 18,000–45,000 | Roof area, access, material and structural condition |
Appliances, authority fees, condo deposits and hidden repairs are excluded unless your written quotation includes them.
WHAT CHANGES THE NUMBER
A finish is more than its colour. We compare the material, hardware and fitting work before you choose.

A larger room needs more materials and labour. Cabinet length and tile area matter more than the room name.
Board, worktop, tile and drawer fitting choices can change the cost substantially.
Removing old finishes and rebuilding the base can take more work than a surface refresh.
Changing sink, drainage or electrical locations adds work behind the walls.
Condo lifts, restricted work hours, stairs and delivery access affect time and handling.
THE DETAIL BEHIND THE TOTAL
An 18 ft kitchen, keeping the main layout, with plywood cabinets, quartz worktop and new tiles. Appliances and any extension are outside this scope.
| Work item | Quantity | Amount |
|---|---|---|
| Site protection, hacking & debris removal | 1 lot | RM 3,200 |
| Floor & wall tiles, preparation and laying | 1 lot | RM 5,800 |
| Wet works & waterproofing | 1 lot | RM 1,800 |
| Plywood cabinets with laminate finish | 18 ft | RM 14,400 |
| Quartz worktop & fitting | 18 ft | RM 6,000 |
| Plumbing points & sink installation | 1 lot | RM 2,400 |
| Electrical points & task lighting | 1 lot | RM 2,600 |
| Sink, tap & cabinet accessories | 1 lot | RM 1,800 |
| Finishing, testing & final clean | 1 lot | RM 2,000 |
| Total for the agreed scope | RM 40,000 | |
A written quote also lists the exact material selections, exclusions, payment milestones, warranty scope and handover date. Any applicable tax is stated before you accept.
Get a quote for your homeYOUR BUDGET STAYS YOURS
If we uncover a hidden issue, we photograph it, explain your options and provide the cost and schedule impact. You approve the change in writing before that work starts.
LET’S MAKE ROOM FOR BETTER
We will visit, measure and send a written quote in 3 working days.
No obligation. No pressure to decide on the day.