PROJECT STORY · BUKIT BARU

A fresh start for a
Bukit Baru family home.

A 20-year-old double-storey terrace, brought up to date for a family moving back to Melaka.

PropertyDouble-storey terrace
Time on site12 weeks
Final cost rangeRM 108,000–118,000
Site supervisorDaniel Tan

THE STARTING POINT

What the family
needed to change.

The house had been rented out for years. The family wanted to move home, but the old wiring, tired floors and cramped kitchen needed attention first. Their priority was a safe, clean home ready before the new school term.

The brief we agreed

  • Keep the structure and focus on daily living
  • Replace worn services before covering them
  • Put the bigger costs into useful, durable finishes
  • Agree a handover date the family could plan around

BEFORE & AFTER

Same viewpoint. A different feeling.

After renovation: Bukit BaruBefore renovation: Bukit BaruBeforeAfter↔

Bukit Baru

Double-storey terrace · 12 weeks · RM 108,000–118,000

WHAT WE DID

The decisions behind the result.

Safe services first

We checked and replaced the agreed wiring and plumbing before wall and floor finishes.

Rooms that work together

The living area, kitchen and storage were planned as one everyday route through the house.

A finish ready to live in

Fresh floors, ceilings, paint and carpentry gave the family a practical, consistent home.

Supervisor reviewing the renovation with the crew

HOW THE JOB STAYED ON TRACK

One supervisor.
A daily picture of progress.

The family received a short WhatsApp update each working day: what was finished, what was next and any choice we needed from them.

  • A 12 weeks written schedule before site work began
  • Material choices confirmed before ordering
  • Any extra scope priced and approved in writing
  • A joint walkthrough and touch-ups before final payment

Old wiring was found in the kitchen wall. Daniel shared photographs, explained the options and confirmed the approved replacement cost before continuing. The updated sequence kept the handover date intact.

WHERE THE BUDGET WENT

A cost you can
make sense of.

The final agreed scope included these work groups. Materials and quantities were set out in the signed quotation.

Loose furniture and appliances were outside this scope. The final payment was held until the agreed touch-ups were complete.

Essential wiring & plumbingRM 22,000
Wet works & floorsRM 29,000
Kitchen & built-in carpentryRM 32,000
Ceilings, painting & finishingRM 22,000
Protection, disposal & handoverRM 7,000
Agreed project totalRM 112,000
Crew carrying out the final clean in the renovated Bukit Baru living room

THE FINISH INCLUDES THE CLEANUP

Ready to move
back in.

The team removes the agreed work waste and cleans the renovated areas before the final walkthrough. You can focus on checking the home, with your supervisor beside you.

  • Renovated surfaces wiped down
  • Work waste and floor protection removed
  • Fittings checked and touch-ups recorded
★★★★★
“The quote was detailed enough for us to understand where the money went. There was old wiring that needed replacing, but Daniel showed us first and gave the cost before doing anything. Handover was on the date in our schedule.”
Azlan

Bukit Baru · Whole house

MORE TO EXPLORE

Another home. Another useful change.

LET’S MAKE ROOM FOR BETTER

Tell us what you
want to change.

We will visit, measure and send a written quote in 3 working days.

No obligation. No pressure to decide on the day.

WhatsAppFree site visit

A CLOSER LOOK

From old kitchen to everyday favourite.

Read the full project