PROJECT STORY · AYER KEROH

A calmer
morning routine.

A tired bathroom in Ayer Keroh, rebuilt for better drainage, easier cleaning and a more comfortable start to the day.

PropertyTerrace bathroom
Time on site3 weeks
Final cost rangeRM 14,000–17,000
Site supervisorHafiz Rahman

THE STARTING POINT

Why the owner
called us.

Water lingered on the old floor after a shower, the fittings were tired, and the family wanted to deal with the wet-area concerns before replacing the tiles. The aim was a practical bathroom with a proper base, clear drainage and a finish that was easier to keep clean.

The brief we agreed

  • Rebuild the floor with a fall towards the drain
  • Replace the agreed plumbing and tired fittings
  • Test the specified waterproofing before tiling
  • Keep shared access tidy while the family stayed at home

BEFORE & AFTER

The work, made visible.

Drag the line to compare the same viewpoint before and after the agreed work.

After renovation: Ayer KerohBefore renovation: Ayer KerohBeforeAfter↔

Ayer Keroh

Terrace bathroom · 3 weeks · RM 14,000–17,000

WHAT WE DID

The decisions behind the result.

Start below the tiles

The team removed the agreed old finishes, prepared the base and checked the drainage route before rebuilding the floor.

Test before covering up

The specified waterproofing was applied and ponding-tested before new tiles were laid.

Make daily use easier

A glass shower screen, practical basin and simpler fittings made washing and cleaning more straightforward.

THE AGREED SCOPE

The work behind
the finished space.

  • Protection, hacking and removal of agreed old finishes
  • Plumbing work and floor falls to the drain
  • Specified waterproofing system and ponding test
  • New floor and wall tiles in the agreed range
  • WC, basin, shower fittings and glass screen installation
  • Drainage checks, final clean and handover touch-ups

The quotation listed the exact materials, quantities, exclusions and payment milestones. Extra work needed written approval before proceeding.

Finished bathroom fittings, tile joints and glass screen

THE WORK, IN ORDER

A schedule the owner could follow.

The family had another usable bathroom during the work. The dusty days and access route were agreed before the three-week site schedule began.

01

Days 1–3

Protect & remove

Protect the access route and remove the agreed fittings, tiles and worn base materials.

02

Days 4–7

Base & waterproofing

Prepare the floor falls and plumbing points, apply the specified waterproofing and complete its test period.

03

Week 2

Tiles & finish work

Lay the selected tiles after the agreed checks and allow the required curing time.

04

Week 3

Install & test

Fit the WC, basin, shower and screen. Check water flow and drainage together.

05

End of week 3

Walk through & close

Clean the room, record touch-ups and fix the agreed defects before the final payment.

Waterproofing applied to a bathroom floor around a drain

CHECKED BEFORE HANDOVER

The check you
cannot see afterwards.

The new tiles were only one part of this job. Hafiz recorded the waterproofing test and checked the floor drainage before the bathroom was handed back to the family.

  • Waterproofing tested before tiling
  • Water flow and floor drainage checked
  • Tap connections and waste joints inspected
  • Shower screen, door clearances and silicone joints reviewed

WHERE THE BUDGET WENT

A cost you can
make sense of.

These work groups made up the final agreed scope. Exact material choices and exclusions were shown in the written quotation.

The agreed total sat within the RM 14,000–17,000 project range.

Payments followed written milestones, with the final 5% held until the agreed handover defects were fixed.

Protection, hacking & disposalRM 1,500
Plumbing & floor fallsRM 2,100
Waterproofing & ponding testRM 1,500
Floor & wall tilingRM 4,200
Sanitaryware & fittingsRM 3,400
Glass shower screenRM 1,600
Checks, finishing & final cleanRM 1,300
Agreed project totalRM 15,600

THE HANDOVER

A finish the owner
could check.

  • Water drains towards the floor waste
  • Fewer awkward corners to clean
  • New fittings checked with the homeowner

The written scope includes a 12 month workmanship warranty and five years on the specified waterproofing system and areas. Product warranties follow the maker’s terms.

Plan a similar bathroom
Completed Ayer Keroh bathroom project
★★★★★
“Hafiz explained the waterproofing test before the tiles went down. The team cleaned the walkway each day, which my mother appreciated. Three weeks from start to finish, including a small touch-up around the door.”
Siva

Ayer Keroh · Bathroom

LET’S MAKE ROOM FOR BETTER

Tell us what you
want to change.

We will visit, measure and send a written quote in 3 working days.

No obligation. No pressure to decide on the day.

WhatsAppFree site visit

A CLOSER LOOK

From old kitchen to everyday favourite.

Read the full project