BeforeAfter↔Ayer Keroh
Terrace bathroom · 3 weeks · RM 14,000–17,000

PROJECT STORY · AYER KEROH
A tired bathroom in Ayer Keroh, rebuilt for better drainage, easier cleaning and a more comfortable start to the day.
THE STARTING POINT
Water lingered on the old floor after a shower, the fittings were tired, and the family wanted to deal with the wet-area concerns before replacing the tiles. The aim was a practical bathroom with a proper base, clear drainage and a finish that was easier to keep clean.
BEFORE & AFTER
Drag the line to compare the same viewpoint before and after the agreed work.

BeforeAfter↔Terrace bathroom · 3 weeks · RM 14,000–17,000
WHAT WE DID
The team removed the agreed old finishes, prepared the base and checked the drainage route before rebuilding the floor.
The specified waterproofing was applied and ponding-tested before new tiles were laid.
A glass shower screen, practical basin and simpler fittings made washing and cleaning more straightforward.
THE AGREED SCOPE
The quotation listed the exact materials, quantities, exclusions and payment milestones. Extra work needed written approval before proceeding.

THE WORK, IN ORDER
The family had another usable bathroom during the work. The dusty days and access route were agreed before the three-week site schedule began.
Days 1–3
Protect the access route and remove the agreed fittings, tiles and worn base materials.
Days 4–7
Prepare the floor falls and plumbing points, apply the specified waterproofing and complete its test period.
Week 2
Lay the selected tiles after the agreed checks and allow the required curing time.
Week 3
Fit the WC, basin, shower and screen. Check water flow and drainage together.
End of week 3
Clean the room, record touch-ups and fix the agreed defects before the final payment.

CHECKED BEFORE HANDOVER
The new tiles were only one part of this job. Hafiz recorded the waterproofing test and checked the floor drainage before the bathroom was handed back to the family.
WHERE THE BUDGET WENT
These work groups made up the final agreed scope. Exact material choices and exclusions were shown in the written quotation.
The agreed total sat within the RM 14,000–17,000 project range.
Payments followed written milestones, with the final 5% held until the agreed handover defects were fixed.
THE HANDOVER
The written scope includes a 12 month workmanship warranty and five years on the specified waterproofing system and areas. Product warranties follow the maker’s terms.
Plan a similar bathroom
“Hafiz explained the waterproofing test before the tiles went down. The team cleaned the walkway each day, which my mother appreciated. Three weeks from start to finish, including a small touch-up around the door.”Siva
Ayer Keroh · Bathroom
LET’S MAKE ROOM FOR BETTER
We will visit, measure and send a written quote in 3 working days.
No obligation. No pressure to decide on the day.