Completed terrace house rear extension

PROJECT STORY · CHENG

Room for a proper
wet kitchen.

A rear extension in Cheng that gave everyday cooking, washing and storage a sheltered, useful place of their own.

PropertyDouble-storey terrace
Time on site9 weeks
Final cost rangeRM 52,000–60,000
Site supervisorDaniel Tan

THE STARTING POINT

Why the owner
called us.

The rear working area was exposed and short on useful space. Washing and heavier cooking competed for the same small counter, and the family wanted shelter without making the back of the house feel shut in.

The brief we agreed

  • Create a practical covered wet-kitchen area
  • Plan the structure, roof junction and drainage together
  • Keep useful openings for daylight and air movement
  • Agree approvals, materials and the build sequence before work

BEFORE & AFTER

The work, made visible.

Drag the line to compare the same viewpoint before and after the agreed work.

After renovation: ChengBefore renovation: ChengBeforeAfter↔

Cheng

Double-storey terrace · 9 weeks · RM 52,000–60,000

WHAT WE DID

The decisions behind the result.

Check the structure first

The existing house and rear working area were reviewed before the foundation and structural scope were confirmed.

Plan how rain leaves

The roof junction, rainwater route and floor drainage were considered as part of the build.

Keep the working area useful

The counter, washing points and storage were placed around daily cooking while preserving the agreed openings.

THE AGREED SCOPE

The work behind
the finished space.

  • Measured layout, drawings and agreed permit coordination
  • Site preparation and listed foundation work
  • Agreed structural frame, walls and roof construction
  • Roof junctions, rainwater goods and drainage
  • Plumbing and electrical points for the wet kitchen
  • Floor finishes, plaster, paint and listed counter fittings
  • Final water checks, cleaning and joint handover

The quotation listed the exact materials, quantities, exclusions and payment milestones. Extra work needed written approval before proceeding.

The original rear working area before the extension

THE WORK, IN ORDER

A schedule the owner could follow.

Council requirements, drawings and any required professional input were resolved before construction. Approval and preparation time were kept separate from the nine-week on-site schedule.

01

Week 1

Prepare & set out

Protect the access route, set out the agreed footprint and prepare for foundation works.

02

Weeks 2–4

Build the structure

Complete the agreed foundations, frame, walls and roof in the planned sequence.

03

Weeks 5–6

Services & wet works

Install the listed plumbing, wiring, drainage and roof-junction details.

04

Weeks 7–8

Finishes & fittings

Complete tiles, plaster, painting and the agreed wet-kitchen counter and fittings.

05

Week 9

Check & hand over

Review water routes, fittings and finish quality. Close the agreed touch-ups and clean the work area.

Workers checking masonry and a structural beam during extension work

CHECKED BEFORE HANDOVER

A careful connection
to the existing home.

Daniel checked the agreed structural details and the junction between old and new work before the finishes closed them in. Photos made those stages visible to the family.

  • Agreed structural details reviewed before finishing
  • Roof and wall junctions checked
  • Rainwater and floor drainage routes reviewed
  • Fittings and clearances tested at handover

WHERE THE BUDGET WENT

A cost you can
make sense of.

These work groups made up the final agreed scope. Exact material choices and exclusions were shown in the written quotation.

The agreed total sat within the RM 52,000–60,000 project range.

Payments followed written milestones, with the final 5% held until the agreed handover defects were fixed.

Drawings & agreed permit coordinationRM 3,500
Site preparation & foundationsRM 10,500
Structure, masonry & roofRM 21,500
Plumbing, drainage & electrical workRM 6,000
Tiles, plaster & paintingRM 7,500
Wet-kitchen counter & fittingsRM 5,000
Checks, finishing & cleanupRM 2,000
Agreed project totalRM 56,000

THE HANDOVER

A finish the owner
could check.

  • A sheltered area for cooking and washing
  • Storage and service points planned together
  • Rear openings retained for light and air

Workmanship and the specified waterproofing scope are set out in the written warranty. The handover documents identify the covered areas, product terms and who to contact.

Plan your home extension
Completed Cheng extension project
★★★★★
“Daniel explained the work at the back before we agreed the quote. The daily photos helped because we could not be at home every day. The nine-week site plan was useful, and we checked the drainage and finishes together before the last payment.”
Nurul

Cheng · Extension

LET’S MAKE ROOM FOR BETTER

Tell us what you
want to change.

We will visit, measure and send a written quote in 3 working days.

No obligation. No pressure to decide on the day.