PROJECT STORY · MELAKA RAYA

Ready for the
first customer.

A small service studio in Melaka Raya, fitted out with a welcoming reception, useful storage and a clear route for customers.

PropertyGround-floor shoplot
Time on site6 weeks
Final cost rangeRM 42,000–48,000
Site supervisorDaniel Tan

THE STARTING POINT

Why the owner
called us.

The owner was taking over a tired commercial unit and needed a practical front-of-house space before opening. The reception desk, waiting area, lighting and storage all had to work within a compact footprint.

The brief we agreed

  • Make the entrance and reception easy to understand
  • Provide useful counter and storage space
  • Create a comfortable waiting area
  • Coordinate the fit-out around an agreed opening plan

BEFORE & AFTER

The work, made visible.

Drag the line to compare the same viewpoint before and after the agreed work.

After renovation: Melaka RayaBefore renovation: Melaka RayaBeforeAfter↔

Melaka Raya

Ground-floor shoplot · 6 weeks · RM 42,000–48,000

WHAT WE DID

The decisions behind the result.

Start with the visitor route

The reception point is visible from the entrance, with a clear path between the door, counter and waiting area.

Build useful storage in

The measured reception desk and shelving give everyday supplies their own places.

Coordinate the trades

Electrical points, ceiling work, painting and joinery followed one sequence before final checks.

THE AGREED SCOPE

The work behind
the finished space.

  • Site protection, strip-out and agreed preparation work
  • Listed partitions and wall preparation
  • Electrical points, lighting and ceiling work
  • Floor finishing and agreed entrance adjustments
  • Measured reception desk and built-in storage
  • Painting, fitting checks, final clean and handover

The quotation listed the exact materials, quantities, exclusions and payment milestones. Extra work needed written approval before proceeding.

The commercial unit before its reception fit-out

THE WORK, IN ORDER

A schedule the owner could follow.

The six-week on-site plan began after the owner confirmed finishes and access arrangements. Loose business equipment, signage and approval responsibilities were kept clear in the quotation.

01

Week 1

Prepare the unit

Protect access, remove the listed old finishes and confirm final site measurements.

02

Week 2

Services & partitions

Complete the agreed partitions, electrical points and concealed service work.

03

Weeks 3–4

Ceilings & finishes

Coordinate ceiling, flooring, wall preparation and painting in the planned order.

04

Week 5

Joinery & lighting

Install the reception desk and storage, then fit and check the agreed lights.

05

Week 6

Check & get ready

Walk through the customer areas, close agreed touch-ups and complete the final clean.

Cabinet boards, worktop material and hardware selected for a fit-out

CHECKED BEFORE HANDOVER

Choose the finishes.
Then coordinate the work.

The owner confirmed the counter dimensions, materials and lighting choices before ordering. That gave the trades a clear plan and reduced late changes near opening day.

  • Reception dimensions and clearances checked
  • Lighting and agreed electrical points tested
  • Cabinet doors, shelves and hardware reviewed
  • Work waste removed and customer areas cleaned

WHERE THE BUDGET WENT

A cost you can
make sense of.

These work groups made up the final agreed scope. Exact material choices and exclusions were shown in the written quotation.

The agreed total sat within the RM 42,000–48,000 project range.

Payments followed written milestones, with the final 5% held until the agreed handover defects were fixed.

Protection, strip-out & disposalRM 2,400
Partitions & wall preparationRM 5,600
Electrical work & lightingRM 8,800
Ceilings & paintingRM 6,600
Reception desk & built-in storageRM 13,200
Floor finishes & entrance workRM 5,000
Fitting checks, finishing & final cleanRM 3,400
Agreed project totalRM 45,000

THE HANDOVER

A finish the owner
could check.

  • A clear reception point at the entrance
  • Storage built around daily business use
  • Customer areas checked and cleaned before opening

The agreed installation work carries the written workmanship warranty. Product warranties follow their makers’ terms, and any later changes by other trades are reviewed against the original scope.

Plan your shop or office fit-out
Completed Melaka Raya shop project
★★★★★
“Daniel asked how customers would use the front area before planning the counter. We had one clear schedule for the ceiling, wiring and carpentry. The six-week fit-out gave us time to arrange our equipment, and the team dealt with the small touch-ups before handover.”
Lina

Melaka Raya · Shop

LET’S MAKE ROOM FOR BETTER

Tell us what you
want to change.

We will visit, measure and send a written quote in 3 working days.

No obligation. No pressure to decide on the day.

WhatsAppFree site visit

A CLOSER LOOK

From old kitchen to everyday favourite.

Read the full project